Project Construction is currently on pace to begin at the beginning of June.
This project will involve street improvements to the following sites:
The 2025 street preservation efforts include resurfacing aging roadway surfaces, as well as updating nearby sidewalk ramps to current federal standards. When the streets are resurfaced, the process typically involves grinding away the top two or three inches of existing asphalt and then repaving with new asphalt to original grade.
April 7: Bid Advertisement
April 24: Bid Open
May 13: Bid Award
June 2: Begin Project Construction
July 25: End Project Construction
December 2025: Project Completion
*Title VI: It is the City of Monroe’s policy to assure that no person shall on the grounds of race, color, or national origin as provided by the Title VI of the Civil Rights Act of 1964, be excluded from participating in, be denied the benefits of, or be otherwise discriminated against under any of its programs or activities. If you have questions about this program, please contact pwcontracts@monroewa.gov.