2020 Annual Paving Project

Project Description

The City has established a Transportation Benefit District (TBD) to help maintain existing streets. Engineering staff utilize the StreetScan program that helps determine the best use of TBD funds in order to maximize maintenance efforts toward our citywide street system. Maintenance efforts include practices such as overlaying with new asphalt, adding new aggregate to the road surface (chip sealing), replacing lost binder oils on the surface (fog seal), and filling in cracks with elastomeric material (crack sealing). Some street segments are identified for only preservation, while others are paired up with utility reconstruction needs that collectively form a complex project and take a year or two to accomplish. In addition, existing sidewalk ramps adjacent to the project areas are reviewed and reconstructed as necessary to be compliant with current ADA standards.

City of Monroe engineering staff completed the design and are administering the construction contract for the 2020 Annual Road Maintenance Project. The work includes placement of hot mix asphalt, pavement repair, planing or grinding, construction of ADA ramps, pavement markings, utility adjustments, traffic control and other associated work. This project also includes updating pavement markings (e.g., striping, crosswalks, stop lines, and traffic arrows) at various locations throughout the City. These locations are in addition to the replaced markings associated with the overlay work.

On June 9th, Monroe City Council authorized the 2020 Annual Road Maintenance Contract with Lakeside Industries in the amount of $958,734. The exceptional bid results for this project created an opportunity to preserve additional street segments this year with the remaining budget for 2020. 

Engineering staff prepared a new set of construction documents that provides for street improvements along 154th Street SE, between 167th Avenue SE to 171st Avenue SE. This work spans approximately 1,500 feet along the road and includes four intersections.

Contact Us

  1. Jammi Guion


    Contracts Supervisor
    Email Public Works Contracts
    Phone: 360-863-4514

    Kim Klinkers, PE

    Project Manager
    Email Kim Klinkers
    Phone: 425-760-7895

    Scott Peterson, PE

    Deputy City Engineer
    Email Scott Peterson
    Phone: 360-863-4606


154th Street Overlay Project Update

Week 1: August 17th to August 21st

The contractor will post project notice signs and began curb ramp demolition. Sidewalks are still open and accessible for pedestrians.

August 2020

Engineering staff are working with Cadman Materials to execute this construction contract. The pre-construction meeting took place on August 4th, and construction work should commence on August 17th.

The construction window is anticipated to span two months, with most work substantially complete by October 2020. Project notice signs will be placed before construction work begins. A digital reader board will provide advanced notification for construction activities that require significant traffic impacts, such as pavement grinding or paving.

About 40 public notification postcards were mailed to residents adjacent to the proposed construction work. Information on the postcard included approximate construction timeline, work locations, project description, project website, and staff contact information.

July 2020

The 154th Street Overlay Project was advertised for contractor bids on June 29th and July 6th. The Engineer’s probable cost opinion was $380,000. Six bids were received and opened on July 13th, with bids ranging from $288,709 to $466,820, inclusive of sales taxes.

The following contractors submitted the two lowest bids:

  • Apparent Low: Cadman Materials, Inc. $ 288,709
  • Apparent Second Low: Trinity Contractors $ 298,571

After review, state licensing verification, and reference calls, the lowest responsive bidder is Cadman Materials, Inc. The 154th Street Overlay construction contract was awarded to Cadman Materials by the Monroe City Council at the July 28th regular business meeting.

2020 Annual Road Maintenance Project Update

August 2020

Project wide property restoration, utility adjustments, permanent pavement markings, and cleanup work will occur in August.

Week 4: July 27th to July 31st

Finish paving Village Way on Thursday July 30th.

Week 3: July 20th to July 24th

Pave Tye Street, Beaton Road, and 172nd Drive on Monday and Tuesday (7/20 - 7/21). Grind the road surface on Village Way on Thursday (7/23). Begin paving Village Way on Friday (7/24).

Week 2: July 13th to July 17th

The road surfaces on Cascade View Drive, Tye Street, Beaton Road, and 172nd Drive were ground this week. 177th Avenue and Cascade View Drive have been repaved. Work to reconstruct the concrete curb ramps will be complete this week.

Week 1: July 6th to July 10th

The contractor posted project notice signs and began curb ramp demolition on Beaton Road, 177th Avenue, and Village Way. Sidewalks are still open and accessible for pedestrians. The road surface on 177th Avenue was ground in preparation for new asphalt surfacing.

June 2020

After review, state licensing verification, and reference calls, the lowest responsive bidder is Lakeside Industries, Inc. The 2020 Annual Road Maintenance construction contract was awarded to Lakeside by the Monroe City Council at the June 9th regular business meeting.

Engineering staff are working with Lakeside to execute this construction contract and schedule a pre-construction meeting. The pre-construction meeting is expected to occur late June, with construction activities commencing in July.

The construction window is anticipated to span three to four months, with most work substantially complete by September 2020. Project notice signs will be placed before construction work begins. A digital reader board will provide advanced notification for construction activities that require significant traffic impacts, such as pavement grinding or paving.

About 300 public notification postcards were mailed to residents and businesses adjacent to the proposed construction work. Information on the postcard included approximate construction timeline, work locations, project description, project website, and staff contact information.

April 2020

The 2020 Annual Road Maintenance Project was advertised for contractor bids on April 7th and April 21st. The Engineer’s probable cost opinion was $1,600,000. Six bids were received and opened on April 30th, with bids ranging from $958,734 to $1,602,134, inclusive of sales taxes.

The following contractors submitted the two lowest bids:

  • Apparent Low: Lakeside Industries, Inc. $ 958,734
  • Apparent Second Low: Cadman Materials, Inc. $ 1,267,585

Project Location

The streets included in the 2020 Annual Paving Project are listed in the table below and their approximate locations  are shown on the map.

On Street
From Street
To Street

Tye Street SE

169th Drive SE

Beaton Road SE

Beaton Rd / 147th St SE

169th Drive SE

Tye Street SE

172nd Drive SE

Beaton Road SE

South End

Cascade View Drive

Monroe Co-op

City Limits

177th Avenue SE

W Main Street

City Limits

Village Way

W Main Street loop

W Main Street loop

154th Street SE
167th Avenue SE
171st Avenue SE


paving, overlay, road maintenance, 154